玻璃雨棚做法介绍

发布时间:2024-06-19 来源:https://www.gongyingrui.com/

玻璃雨棚的整体结构使以钢结构框架为主,选用的都是的钢管。一般玻璃采用的都是钢化玻璃,钢化玻璃的强度高,承载能力强,不容易损坏。下面带您了解一下玻璃雨棚做法。

The overall structure of the glass canopy is mainly made of steel frame, and high-quality steel pipes are used. Generally, tempered glass is used, which has high strength, strong load-bearing capacity, and is not easily damaged. Let me take you to learn about the practice of glass canopies.

玻璃雨棚做法

Glass canopy construction method

1、加工准备及下料:按照施工图放样,放样和号料时要预留焊接收缩量和加工余量,根据放样作样板。做好钢材矫正,钢板预埋件及其他零件切割钻孔及喷防腐漆处理。

1. Processing preparation and cutting: According to the construction drawing layout, welding shrinkage and processing allowance should be reserved during layout and marking, and a sample should be made according to the layout. Proper steel correction, cutting and drilling of steel plate embedded parts and other parts, and spraying anti-corrosion paint treatment.

2、测量放线:根据土建标高基准线测预埋件标高中心线,检查预埋件标高偏差、左右偏差。整理结果,确定预埋件分隔的调整处理方案。沿楼板外沿弹出墨线定出预埋件顶标高线。

2. Measurement and laying out: Measure the centerline of the embedded parts according to the civil engineering elevation reference line, and check the elevation deviation and left and right deviation of the embedded parts. Organize the results and determine the adjustment and handling plan for the separation of embedded parts. Pop an ink line along the outer edge of the floor slab to determine the top elevation line of the embedded parts.

3、预埋件安装处理:定位预埋件安装位置,打钻安装。

3. Installation and processing of embedded parts: locate the installation position of embedded parts and drill for installation.

a02e463586b78f6

4、悬挂臂安装焊接。

4. Welding of suspension arm installation.

5、校准检验。

5. Calibration inspection.

6、连接受力拉索:定位拉杆基准线、标高线,按要求安装预埋件,焊接栏杆。

6. Connecting tension cables: locate the reference line and elevation line of the tension rod, install embedded parts as required, and weld the railing.

7、不锈钢玻璃爪安装焊接:按设计尺寸弹出纵横线及设计标高,用夹具夹紧,进行定位点焊,装配完毕,焊接玻璃爪底座。

7. Installation and welding of stainless steel glass claws: Draw vertical and horizontal lines and design elevations according to the design dimensions, clamp with fixtures, perform positioning spot welding, and after assembly, weld the glass claw base.

8、防锈喷漆处理。

8. Anti rust spray painting treatment.

9、夹胶玻璃加工制作安装,偏差不得超过规定偏差。

9. The processing, production, and installation of laminated glass shall not exceed the specified deviation.

10、调整检验:点式玻璃进行整体调整检验,调整标准横平、竖直、面平。偏差不得超过规定偏差。

10. Adjustment inspection: Point glass undergoes overall adjustment inspection, adjusting standards for horizontal, vertical, and surface flatness. The deviation shall not exceed the specified deviation.

11、然后分别进行上下打胶、修补检验、玻璃清洗、清理现场、竣工验收。

11. Then carry out upper and lower gluing, repair inspection, glass cleaning, site cleaning, and final acceptance.